Schedule Variance
Schedule Variance Formula |
| \( SV \;=\; EV - PV \) |
| Symbol |
| \( SV \) = schedule variance |
| \( EV \) = earned value |
| \( PV \) = planned value |
Schedule variance, abbreviated as SV, measure schedule performance that indicates whether a project's schedule is on track or not.