Estimate at Completion
Estimate at Completion Formula |
\( EAC \;=\; AC + \left(BAC - EV\right) \) |
Symbol |
\( EAC \) = estimate at completion |
\( AC \) = actual cost |
\( BAC \) = budget at completion |
\( EV \) = earned value |
Estimate at completion, abbreviated as EAC, is the sum of the actual cost to date and the estimated sum to complete the project.
Estimate at Completion Formula |
\( EAC \;=\; \dfrac{ BAC }{ CPI } \) |
Symbol |
\( EAC \) = estimate at completion |
\( BAC \) = budget at completion |
\( CPI \) = cost performance index |
Estimate at Completion Formula |
\( EAC \;=\; AC + \dfrac{ BAC - EV }{ CPI \cdot SPI } \) |
Symbol |
\( EAC \) = estimate at completion |
\( AC \) = actual cost |
\( BAC \) = budget at completion |
\( CPI \) = cost performance index |
\( EV \) = earned value |
\( SPI \) = schedule performance index |