Percent Complete

 

Percent Complete Formula

\( PC \;=\;  \dfrac{ EV }{ BAC } \cdot 100 \)
Symbol
\( PC \) = percent complete
\( BAC \) = budget at completion
\( EV \) = earned value

Percent complete, abbreviated as PC, is the percentage of a project that has been completed. 