Percent Complete
Percent Complete Formula |
\( PC \;=\; \dfrac{ EV }{ BAC } \cdot 100 \) |
Symbol |
\( PC \) = percent complete |
\( BAC \) = budget at completion |
\( EV \) = earned value |
Percent complete, abbreviated as PC, is the percentage of a project that has been completed.