Estimate to Complete
Estimate to complete, abbreviated as ETC, is the expected cost to finish all the remaining project work.
Estimate to Complete Formula |
\(\large{ ETC = EAC - AC }\) |
Symbol |
\(\large{ ETC }\) = estimate to complete |
\(\large{ AC }\) = actual cost |
\(\large{ EAC }\) = estimate at completion |